Deliverables, milestones and workshops 2007
List of WP7 deliverables during the first period
|
Del. no. |
Deliverable name |
WP no. |
Date due |
Actual/Forecast delivery date |
Used indicative person-months |
Lead contractor |
|
D7.1-1a |
Dissemination and exploitation plan |
7.1 |
Month 3 |
Month 6 updated: Month 13 |
0.5 |
NERSC |
|
D7.1-2a |
Dissemination and promotion activity report (included in updated D7.1-1) |
7.1 |
Month 6 |
Month 6 |
0.4 |
NERSC |
|
D7.1-2b |
Dissemination and promotion activity report (included in updated D7.1-1) |
7.1 |
Month 12 |
Month 13 |
0.1 |
NERSC |
|
D7.2-1 |
Establish web site for the project |
7.2 |
Month 1 |
Month 4 |
0.4 |
CICERO |
|
D7.2-2a |
Updated web site and status report |
7.2 |
Month 6 |
Month 6 |
0.8 |
CICERO |
|
D7.2-2b |
Updated web site and status report |
7.2 |
Month 12 |
Month 12 |
1 |
CICERO |
|
D7.2-3a |
Mobile exhibits to be coordinated with IPY events, open polar days and exhibits at the Polar Centre in Brussels |
7.2 |
Month 12 |
Month 12 |
2.5 |
IPF |
|
D7.3-1 |
High-tech Arctic instrumentation school in Brest |
7.3 |
Month 6 |
Month 11 |
0.25 |
IPEV |
|
D7.3-3 |
A sea ice field course onboard the Russiam icebreaker Kapitan dranitsyn (summer 2007) |
7.3 |
Month 10 |
Month 10 |
2 |
UPMC |
List of WP7 milestones during the first period
|
Mile-stone no. |
Milestone name |
WP no. |
Date due |
Actual/Forecast delivery date |
Lead contractor |
|
M7.1-1a |
Knowledge dissemination and exploitation plan |
7.1 |
Month 3 |
Month 6 |
NERSC |
|
M7.1-2a |
Six-monthly report on dissemination and promotion activities, including promotion material |
7.1 |
Month 6 |
Month 6 |
NERSC |
|
M7.1-2b |
Six-monthly report on dissemination and promotion activities, including promotion material |
7.1 |
Month 12 |
Month 13 |
NERSC |
|
M7.2-1 |
Website completion with general information about the project |
7.2 |
Month 2 |
Month 5 |
CICERO, |
|
M7.2-2a |
Public website and status report on the website |
7.2 |
Month 6 |
Month6 |
CICERO |
|
M7.2-2b |
Public website and status report on the website |
7.2 |
Month 12 |
Month 12 |
CICERO |
|
M7.2-3a |
First version of exhibition/exhibits ready to be used at polar events (IPY) |
7.2 |
Month 12 |
Month 12 |
IPF |
|
M7.3-1 |
Summer School – sea gliders in Brest |
7.3 |
Month 8 |
Month 7 |
UPMC |
List of WP7 workshops during the first period
20—21 June: High-tech Arctic instrumentation workshop in Brest
12-13 September: Arctic GOOS planning meeting in Bergen