Deliverables and milestones 2008
List of WP6 deliverables during the second period
|
Del. no. |
Deliverable name |
WP no. |
Date due |
Actual/Forecast delivery date |
Used indicative person-months |
Lead contractor |
|
D6.1-01b |
Updated User Requirements Document |
6.1 |
Month 18 |
Month 24 |
- |
Met.no |
|
D6.1-02b |
Updated System Design Document |
6.1 |
Month 18 |
Month 21 |
0,25 |
Met.no |
|
D6.2-01 |
DAMOCLES database and interface |
6.2 |
Month 18 |
Month 21 |
10 |
Met.no |
|
D6.2-02 |
Documentation of DAMOCLES database and interfaces |
6.2 |
Month 18 |
Month 21 |
1 |
Met.no |
|
D6.2-03 |
Software tools to aid the data producer submitting the data to the database |
6.2 |
Month 18 |
Month 21 |
3,5 |
Met.no |
|
D6.3-01 |
Future Operational Perspectives Document |
6.3 |
Month 18 |
Month 22 |
0,75 |
DMI |
List of WP6 milestones during the second period
|
Milestone n°. |
Milestone name |
Task n° |
Date due |
Actual/Forecast delivery date |
Lead contractor |
|
M6.1-04 |
Amended User Requirements Document |
T6.1 |
Month 18 |
Month 21 |
MET.NO |
|
M6.1-05 |
Amended System Design Document |
T6.1 |
Month 18 |
Month 21 |
MET.NO |
|
M6.1-06 |
Manuals and guidance papers for data providers |
T6.1 |
Month 18 |
Month 21 |
MET.NO |
|
M6.2-02 |
Final release software tools, including final user manuals and documentation |
T6.2 |
Month 15 |
Month 21 |
MET.NO |
|
M6.2-03 |
Interface prototype including web based data query and visualisation |
T6.2 |
Month 18 |
Month 21 |
MET.NO |