Deliverables and milestones 2007
List of WP4 deliverables during the first period
|
Del. no. |
Deliverable name |
WP no. |
Date due |
Actual/Forecast delivery date |
Used indicative person-months |
Lead contractor |
|
D4.1-1 |
The TOPAZ and the FRAM Strait models, including modeled data, will be provided on required schedule as input to ongoing field operations, especially to the acoustic modeling and inversions taking place in WP 3-Task 1 |
4.1 |
Month 6 |
Month 9 |
1 |
NERSC |
|
D4.2-1 |
Input to a first report on describing the DAMOCLES Acoustic tomography system (Task 3.1). Requirement analysis for data delivery from the tomographic arrays defined by data assimilation needs (TOPAZ) |
4.2 |
Month 12 |
Month 12 |
1 |
NERSC |
|
D4.3-1 |
Preliminary implementation of cost function including observational operators for NAOSIM-DAS completed |
4.3 |
Month 12 |
Month 12 |
7 |
OASys / FastOpt |
|
D4.3-2 |
The HIROMB ocean model is prepared for the Arctic re-analysis |
4.3 |
Month 12 |
Month 12 |
3.55 |
SMHI |
|
D4.3-3 |
MI-IM/MIPOM operational monitoring system delivers daily ice concentration analysis |
4.3 |
Month 12 |
Month 13 |
1.74 |
MET.NO |
List of WP4 milestones during the first period
|
Milestone no. |
Milestone name |
WP no. |
Date due |
Actual/Forecast delivery date |
Lead contractor |
|
M4.1-1 |
Early hindcast model simulations covering years to decades (RCAO, 1D, ORCM) |
4.1 |
Month 9 |
Month 9 |
SMHI |