Deviations from the project Work programme 2008
The following difficulties and logistic problems were met during the second year:
- a partial cancellation of NABOS operations resulting in a lack of possibility to exchange the boundary moorings
- a cancellation of the RV 'Merian' cruise due to technical problems delaying some Damocles operations
- tomography array built but deployment postponed until February 2008
- NP35 drifting near shore due to the lack of perennial ice
- oceanographic instrumentation not deployed in the Russian EEZ
- AITP developed but deployment delayed until April 2008
-
POPS and ITP vulnerability due to fast ice drift
-
CALIB (met buoys) and POPS vulnerability due to lack of buoyancy
Nov 10, 2008